October 2008
Progress work of September, 2008
          Tower A building, For interior work at lift lobbys are finished 97%, corridor finished 90% and room unit finished 40%. Next month, expected project  plan to finish corridor 100% and room unit finished 65%.
          Tower B building, For interior work at lift lobbys are finished 100%, corridor finished 97% and room unit finished 70%. Next month, expected project plan to finish corridor 100% and room unit finished 80%.
          Parking Building, achitectural works at carpark building finished 97%. Interior work at clubhouse finished 98%. Landscape work and finishing work at swimming pool finished 90%. Next month, expected project plan to finish swimming pool 100%.
          Riverside Clubhouse Building, for architectural work at swimming pool and clubhouse finished 99%. We plan to complete swimming pool and clubhouse 100% in October, 2008. and Landscape work at jogging track to finish 100%.
 